Independent Report Runaway of Two Coaches at Bitton, Avon Valley Railway, 25 July 2018
 Photo
The damaged chock - Date? Photographer?


Summary of the Accident
 
On 25 Jul 2018 at around 17:15 hours two empty coaches ran away for approximately 40 metres during shunting operations at Bitton station on the Avon Valley Railway.
 
A small diesel engine and another coach had been uncoupled from the two coaches as the first part of a shunting operation to re-form the train for the following day's operations.
 
The uncoupled coaches began to run away along the platform loop line on which they had been stabled, down a gradient, towards a gated cycle and footpath crossing.
 
Fortunately the coaches stopped when the flange of the right hand wheel of the leading axle of the first coach became stuck in the converging switch and stock rails of a set of points.
 
At the same time, the leading coach collided with the level crossing gate, bending it and pushing it open over about one third of the width of the crossing.
 
The level crossing is for pedestrians and cyclists using the Bristol and Bath Railway Path, a 13 mile (20.9 kilometre) route running between Bath and Bristol city centres.
 
The gates are usually closed against the railway to permit pedestrians and cyclists free access.
 
When a train needs to run over the crossing, a crossing keeper closes the gates across the pathway.
 
The railway path was busy at the time of the accident, and CCTV evidence shows that two cyclists and one pedestrian passed over it in the twenty seconds before the coaches struck the gate.
 
Cause of the Accident
 
The accident happened because the two coaches were not properly secured after they were uncoupled from the locomotive, which had its parking hand brake applied, and the third coach.
 
The coaches, of the British Railways Mark 1 design dating from the 1950s, were equipped with vacuum brakes, but these are only effective once vacuum has been created in the actuating cylinders and reservoirs.
 
The brakes are applied when vacuum in the pipes connecting the vehicles is destroyed, or if the pipes are disconnected.
 
When coaches are stabled, the vacuum in the cylinders and reservoirs will leak away over time, making the brakes on the vehicles ineffective.
 
None of these coaches was fitted with a hand brake.
 
In order to uncouple, the driver was asked by the shunter to "ease up" to enable the coupling to be released, without a vacuum having been created in the rear two coaches.
 
The "easing up" movement compressed the buffers.
 
On being uncoupled, the energy stored in this way gave an impulse to the coaches, which started them moving, and overcame the chocks which were intended to restrain them.
 
Two wooden chocks, which were not the correct profile for the wheels of the coaches, had been placed against two wheels, both on the same axle.
 
Only a visual check had been done to check the chocks were present, rather than a physical check to ensure the chocks were correctly and firmly up against the wheels to prevent any movement.
 
When the coaches began to move, one of the chocks was pushed aside and damaged, and the other was destroyed (see attached images).

 Photo
The remains of the destroyed chock - Date? Photographer? - AVR.

One of the recommendations from the Avon Valley Railway's own investigation into this accident was that prior to dividing rakes, the vacuum should be created and then destroyed to create an automatic brake, removing the reliance on the chocks preventing any unintended movement.
 
This instruction was not previously captured in any Avon Valley Railway documentation.
 
There was no trap point or other mitigation (such as a braked vehicle or derailer) in place to prevent vehicles from running away from where they were stabled onto the main line, over the level crossing, and continuing for nearly 1.5 miles (2.4 kilometres) to Avon Riverside, the Avon Valley Railway's southern terminus (as the downhill gradient continues until close to the end of the line).
 
On UK railways, trap points or derailers have historically been provided at the exits from sidings to prevent vehicles which move away from where they have been stabled from impinging on running lines.
 
The Office and Rail and Road's Goal setting principles for Railway Health and Safety (January 2017) principle 3.7, Stabling areas safe for people.
 
The railway system should provide for the safe marshalling, stabling, servicing, and maintenance of trains.
 
In order to achieve the outcome, paragraph 3.7c states that railways should at least consider any incline in relation to runaway trains.
 
The sidings at Bitton are equipped with these devices, but the platform loop line, which is used by passenger trains, is not.
 
For many years, the railway has stabled vehicles in this loop.
 
Witness evidence indicates that usually, when coaches are stabled there is a braked vehicle (ie a coach equipped with a hand brake) at the downhill end of the rake.
 
However, the railway only has two such vehicles, and at the time of the accident one was at the rear of the passenger train stabled in the adjacent platform line, and the second was undergoing maintenance.
 
Author unknown.