- Construct train staging track at Coquitlam Yard
- Construct second main track at Basque
- Construct grade for future second main track at Savona
- Extend Mnro siding eastward
- Construct additional train crossover between tracks at Benlidi and Tranquille
- Construct train crossovrs beteen main tracks at Ducks - construct locomotive set-off tracks at
Geddis
- Extend double track eastard at Pritchard
- Extend siding westward at Squilax
- Extend double track westward at Notch Hill
- Extend double track wsestword from Tumtum to Clanwilliam
- Starage tracfk extension at lake Louise
- New siding at Gap
- Siding extensions and new signal system at Airdrie
- Siding extensions and new signal system at Beddingon
- New siding and signal system at Bengal
- Communications systems upgrade in Network Management Center (NMC) in Calgary
- New staging track and double track extension with train crossovers between main tracks at
Shepard
- New second main line with train crossoves between Carseland and Dalmead
- Siding extension at Gleichen
- Siding extension at Kininvie
- New staging tracks and double-track extensions with additional train crossovers at Dunmore
- New siding at Maple Creek
- Siding extension at Antelope
- Construct additional train crossovers between main tracks at Swift Current - extend double-track
at Aitkins
- Extend double-track at Seven Mile - construct additional train crossovers between main tracks at
Zola (between Moose Jaw and Seven Mile)
|
|