29 August 2005
CPR Western Capital Projects
Clanwilliam - Well, as of today, the TumTum to Clanwilliam project is basicly
done. The only remaining task is changing the turnout at Clanwilliam to a number 20 turnout but the double track is in
service as of today.
That leaves the Notch Hill project as the only major WestCap project underway on the Shuswap.
The Watmore-Pritchard extension is complete and the minor project at Geddis is almost done. There is already some
surveying going on for possible projects next year.
The Squilax extension is on hold till next year due to problems coming to an agreement with the native band.
|