Extra $20M Required for Wider Floodway

Winnipeg Manitoba - The Manitoba Floodway Authority will spend an additional $20 million to dig a wider channel while scaling back some bridge work to ensure the expansion project stays within the original $665-million budget.
 
Additional excavation means four existing highway bridges - Hwy. 59 North, Hwy. 15, St. Mary's Road and Hwy. 44 - and two existing railway bridges won't need to be raised.
 
Bridge work either completed or still under construction includes the TransCanada, Hwy. 50 South and the Sprague CN Rail bridge.
 
The plan includes the replacement of CN Redditt, CP Emerson, and CP Keewatin railway bridges.
 
 