London Ontario - Adelaide Street North will be closed between McMahen and Elias Streets from
7 to 9 Sep 2023 to lift the second of two rail bridge pieces into place for the Adelaide Underpass
project.
A crane will remove part of the existing temporary rail bridge structure and place the new rail bridge piece on the
north side of the tracks.
Installation of the two new rail bridge pieces is an important milestone that allows the project to progress to
excavation for the underpass itself, which traffic will use to pass beneath the tracks.
LTC Routes 16 and 92 will be detoured along Piccadilly Street, William Street, and Princess Street while this
work is underway.
For the latest detour information visit the London Transit Detours and Stop Closure page.
About the Project
The City of London is reconstructing Adelaide Street North from Elias Street to just north of McMahen Street, and
Central Avenue from William Street to Elizabeth Street.
The project is adding an underpass beneath the rail tracks to allow traffic to continue flowing while trains are
crossing, and adding intersection improvements and active transportation connections through the area, including wide
multi-use paths on both sides of Adelaide Street.
Construction began in spring of 2022, and is scheduled for substantial completion by fall of 2024, with some carryover
work in 2025.
This project has received funding commitments from the Government of Canada and the Province of Ontario to support 10
transit and transit-supportive projects.
Author unknown.
(likely no image with original article)
(usually because it's been seen before)
provisions in Section 29 of the
Canadian Copyright Modernization Act.