Ottawa Ontario - The Trillium Line LRT scored its second straight 100 percent reliability rating on Day 7 of testing.
 
Sunday's perfect score, reported to council Monday in a memo from Richard Holder, director of the Rail Construction Program, Transit Services, marked the fourth time in five days the rating had come in at 100 percent.
 
More importantly, the score boosted the rolling average again, this time to 99.6 percent.
 
TransitNEXT, the consortium that built the Trillium Line, must meet a 98.5 percent reliability rating over the full 14 day trial run.
 
Trial running is still on track to finish up on 21 Oct 2024.
 
Nine diesel trains run on the two tracks of the Trillium Line, with Line 2 between Bayview and Limebank stations and Line 4 the spur from South Keys to the Ottawa airport.
 
A total of 65 operators are needed to keep the trains running on their seven-days-a-week service.
 
According to the scoring system, "on-time" performance means trains must depart within 30 seconds of schedule from each terminus station, Bayview and Limebank for Line 2, and South Keys and the airport for Line 4.
 
When the 14 day trial run is complete, the system will enter a second, seven day period of testing when operators will practise various scenarios including two mock emergency situations, one at the airport and one in the Dow's Lake tunnel, and a day of full-dress rehearsal with volunteer city employees playing the role of commuters on trains and in stations.
 
That week of testing could end as soon as 29 Oct 2024 meaning the Trillium Line could be carrying passengers for real by mid-November.
 
The Trillium Line uses two types of trains, the Stadler FLIRT and Alstom LINT.
 
Unlike the electric-powered Confederation Line, Trillium Line trains run on diesel.
 
Trains run every 12 minutes and can hold up to 600 passengers, with 300 in each of their two cars.
 

The north-south Trillium Line.
The north-south Trillium Line - Date? Cartographer?


Here's what's happened so far during testing:
 
Saturday, 12 Oct 2024
 
For the third time since the start of testing last Monday, the Trillium Line LRT scored a perfect 100 percent reliability rating on Saturday, boosting the rolling average to 99.5 percent.
 
Friday, 11 Oct 2024
 
The Trillium Line scored a 99.4 percent reliability rating on its fifth day of testing Friday, keeping the rolling average to 99.4 percent.
 
Thursday, 10 Oct 2024
 
For the second day running, the Trillium Line LRT scored a 100 percent reliability rating on its fourth day of testing. Thursday's 14 day rolling average was 99.4 percent.
 
Wednesday, 9 Oct 2024
 
The Trillium Line LRT scored a perfect 100 percent reliability rating on its third day of testing. Wednesday brought the 14 day rolling average to 99.3 percent.
 
Tuesday, 8 Oct 2024
 
"We remain on a very positive trend," Richard Holder, director of rail construction for the City of Ottawa, said during a media briefing Wednesday. "It is still early days, but I'm pleased with the results I'm seeing."
 
On Tuesday, one train had a minor issue with a CCTV camera that operators would use to monitor passengers, and another had a minor delay at a terminus station when the operator switched from the controls at one end of the train to the other, Holder said.
 
Monday, 7 Oct 2024 — Trillium Line testing starts.
 
The Trillium Line LRT achieved a 98.3 percent on-time performance during its first full day to trial running on Monday.
 
That was just shy of the 98.5 percent score that builder TransitNEXT must achieve as a rolling average over the full 14 day trial running period, but City of Ottawa Transit General Manager Renee Amilcar said she'd take it.
 
"I'm very, very happy, 98.3 percent is very good, especially for the first day," Amilcar said Tuesday in the first daily briefing to reporters during the testing phase.
 
A minor brake problem delayed the deployment of one of the Trillium Line's nine trains in the morning, while two other trains experienced problems with the CCTV cameras showing the operator the platforms and doors, said Richard Holder, director of rail construction for the city.
 
Blair Crawford.

*1. Suitable news image inserted.
(likely no image with original article)
*2. Original news image replaced.
(usually because it's been seen before)
News quoted by OKthePK under the
provisions in Section 29 of the
Canadian Copyright Modernization Act.