Stonehaven Scotland United Kingdom - British infrastructure manager Network Rail (NR) has announced that the Aberdeen-Dundee main line will reopen on 3 Nov 2020 after repairs following a fatal accident on 12 Aug 2020.
Three people, including the driver Brett McCullough, conductor Donald Dinnie, and passenger Christopher Stuchbury, were killed when the 06:38 ScotRail Aberdeen-Glasgow service struck a land slip following heavy rain.
The incident at Carmont, near Stonehaven, caused extensive damage to the track, bridge, embankments, and drainage systems.
NR says its engineers have been working around the clock since the incident, initially supporting the accident investigation before beginning work in September to recover the derailed coaches and repair and reopen the line.
This work has included:
- building a new 900m road and temporary bridges over the surrounding farmland to bring specialist lifting equipment to the site;
- constructing a 600 tonne crawler crane to lift the derailed coaches from the line;
- replacing more than 500m of damaged track, 70m of bridge parapets and relaying 400m of telecoms cables;
- repairing and enhancing drainage systems and flood defences above and below the line;
- rebuilding the embankment beneath the accident site.
"We continue to work closely with accident investigators as we seek to learn the lessons of this tragedy and make our railway as safe as possible for our people and our passengers. Our thoughts continue to be with the families and friends of Brett, Donald, and Christopher and with the other passengers and colleagues who were affected by the accident," says Alex Hynes, managing director of ScotRail.
ScotRail has been operating a shuttle service between Aberdeen and Stonehaven and between Montrose and Edinburgh.
Replacement bus services have also been in place between Aberdeen and Edinburgh, providing a connection to cross-border rail services.
NR introduced a range of additional safety measures following the incident, including inspecting hundreds of sites with higher-risk trackside slopes across Britain.
These inspections were carried out by NR's in-house engineers and specialist contractors, supplemented by helicopter surveys.
NR has also launched two task forces, led by independent experts, as part of its long-term response to climate change and the challenge of maintaining its massive portfolio of earthworks including embankments and cuttings, many of which date from the 1800s.
Dame Julia Slingo, the former chief scientist at the Met Office, and a world-renowned expert in climatology, is leading a weather action task force with the objective of better equipping NR to understand the risk of rainfall to its infrastructure, drawing on the latest scientific developments in monitoring, real-time observations, and weather forecasting.
Lord Robert Mair, Head of the Cambridge Centre for Smart Infrastructure and Construction (CSIC), is spearheading an earthworks management task force to see how NR can improve the management of its earthworks portfolio, looking at past incidents, latest technologies, innovations and best practice from across the globe.
NR says it already invests heavily in earthworks and drainage, with spending increasing in recent years from £550 million for control period (CP5) between 2009 and 2014 to a budget of £1.3 billion for the CP6 between 2019 and 2024 period.
David Burroughs.
(because there was no image with original article)
*2. Original news article image replaced.
(usually because it's been seen before)
under the provision in Section 29
of the Canadian Copyright
Modernization Act.