Internal link  Image
 Internal link  Image
 Internal link  Image  Internal link  Image  Internal link  Image
 Photo
A Union Pacific double-stack clears a Donner Pass tunnel - Date? Photographer? - UP.
 External link
23 November 2009
Union Pacific Railroad Opens Donner Pass Tunnel to Double-Stack Intermodal Container Freight Traffic

Union Pacific Railroad opened its Donner Pass route to domestic double-stack intermodal container freight traffic 19 Nov 2009 marking the completion of a 12 month project designed to move customer products over a shorter, faster, and more efficient route.
 
"The Donner Tunnel project is a great example of how Union Pacific capital investments continue to support our customers' ability to grow, drive increased operating efficiencies for our railroad, and improve America's transportation infrastructure. Union Pacific has invested nearly US$17 billion in our rail network since 2004 and remains committed to running the railroad as efficiently as possible while providing customers with the highest levels of service," said Jim Young, Union Pacific chairman and chief executive officer.
 
The construction project included:

  • More than 18,000 linear feet of notching to improve tunnel clearances in 15 restricted tunnels between the California cities of Rocklin and Truckee;
     
  • Upgrading 30 miles of system signals to centralized traffic control standards, thus eliminating dark territory and allowing signal technology to control train movement instead of radio communications between dispatchers and locomotive engineers;
     
  • Removing track, lowering the floor, and reinstalling track in two tunnels;
     
  • Installing rock bolts for added stability in five tunnels.

"This project will benefit our customers by improving our intermodal transit times compared to the current Feather River Canyon route. Completing this project will help us better serve our customers while supporting economic growth in Northern California and at the Port of Oakland," said John Kaiser, Union Pacific vice president and general manager intermodal.
 
Union Pacific's Donner Pass route is as much as 75 miles shorter and up to three hours faster than the Feather River Canyon route, depending upon the destination.
 
"Our Feather River Canyon route will continue to play a strategic role in how we serve our customers. The combined benefits of the Donner Pass improvements and our existing Feather River Canyon route will provide additional flexibility to our network as we strive to improve upon Union Pacific's record levels of customer satisfaction," Kaiser said.
 
In addition to utilizing the Donner Pass route for double-stack container rail traffic, the completed construction project provides Union Pacific the ability to operate up to 9,000 foot trains, a 58 percent increase over the 5,700 foot trains that run through Feather River Canyon.
 
A single Union Pacific intermodal train takes up to 300 over-the-road trucks off America's congested highways, reducing highway congestion and repair costs, particularly over the busy I-80 highway system.
 
In addition, rails are 3-4 times more fuel efficient than trucks, resulting in fewer greenhouse gas emissions.
 
Author unknown.

*1. Appropriate news article image inserted.
*2. Original news article image replaced.
News quoted by OKthePK website under the
provisions in Section 29 of the Canadian
Copyright Modernization Act.